Robbins Power Redevelopment Site
Robbins, Cook County, IL · Cal-Sag Channel, about 18 miles south of downtown Chicago
About 16 acres of former power-generation land on the Cal-Sag Channel, about 18 miles south of downtown Chicago. LandUp has the site under contract and is developing it as a power-first campus: a grid reconnection with a temporary gas bridge, targeting about 50 MW first and scalable toward 100 MW. No utility has committed capacity or a date.
- Land
- 16 acres
- Potential total power
- 50 to 100 MW
- Time to first power
- 6 to 18 months
Aerial view · Imagery © Google

127th Street Industrial Site
127th Street, south Chicago, IL · Little Calumet River
A former steel coil plant on about 21 acres close to a 138 kV transmission line: 175,000 SF, 44 ft clear, rail into the building and overhead cranes. A fast-moving site with a defined power route: an on-site substation off the nearby line.
- Land and building
- 21 acres
- Potential total power
- 150+ MW
- Time to first power
- 2.5 to 4 years
Aerial view · Imagery © Google

Polk Street Multi-Level Building
West Loop, Chicago, IL
A three-level building with a basement near downtown Chicago, a short walk from a 138 kV substation and dense fiber. About 0.5 to 1 MW of existing service and a small gas service are on site, and ComEd is evaluating a 10 MW upgrade.
- Building
- 3 levels
- Potential total power
- 10 MW
- Time to added power
- About 12 months
Aerial view · Imagery © Google

Cicero Industrial Building Opportunity
Cicero Avenue corridor, south suburban Cook County, IL
About 95,000 SF of a 390,000 SF industrial building on a 20.7-acre lot in the south suburbs, with about 3 MW of existing service reported and a carrier's fiber equipment on site.
- Land and building
- 20.7 acres
- Potential total power
- Not yet set
- Time to first power
- Not yet set
Aerial view · our target area is part of this building (about 95,000 SF of 390,000 SF) · Imagery © Google
More sites, from 1 MW to 100 MW and beyond
Alongside these sites, LandUp tracks about 10 more locations with roughly 1 to 4 MW of existing power each, positioned along fiber routes. Most of our work sits under 100 MW, and some sites support more. We fit the build to the site: modular where speed matters, conventional where it fits better. Contact us for the list.